The Re-Baseline via Change Request process is a simple method for a member of the project (who has the ability to create change requests) to request a re-baseline of the project without the project manager having to perform it.

First, the user must create the change request. The user must then start the process within the change request by using the Processes tab. Once started, the process will route an action item to the Project Manager. If rejected, the process will end and the user must start it again (if needed). If approved, the process will then baseline the project and close out the change request.

Download Details
Submission Date Jul 17, 2012 12:03 pm
Submitter Rego
Content Type Other
Database Architecture Oracle
Work Type
Work Categories
Related Content
Supported Versions 12.x, 13.x, 14.x, 15.x
Special Instructions Action Baseline Project must have "new revision" drop down value "yes".